Chief Electrical Inspector to Govt

CIEG

Net metering allows selling excess power generated by private entities to DISCOM at a fixed tariff, with approval needed from DISCOM for grid connectivity. CEIG approval is required for electrical installations over 10 KW, including captive power plants, solar power plants, transformers, EHV overhead lines, HT Motors, reactors, and wind power plants. The inspection is carried out under Regulation - 30 and Regulation - 43 before the commencement of supply or after shutdown for more than six months. Inspection is performed under the Central Electricity Authority Regulation 2010, and the Electrical Inspectorate department inspects completed electrical installations.

Process of Inspection

An inspection for CEIG Approval is divided into two parts, the first is the initial inspection, and the other is the periodic inspection by the department. The applications for loads greater than 33 KV are sent to the Chief Electrical Inspector Office, while in the rest of the cases, the application is sent to the Electrical Inspector Office. The cases in which Certification of Electrical Installations by Chief Electrical Inspector is required are as follows.

  • Application for Solar Power plant if electricity generation is above 100 KW
  • Captive Power Plant (CPP) for all purposes (or in case the plant is for construction purposes with a capacity of more than 500 KVA)
  • Transformers
  • EHV Overhead Line
  • HT Motors
  • Reactors
  • Wind Power Plant
Our Features

Application Process for CEIG Approval

Before starting an electrical installation project, the applicant must obtain statutory approval from the Electrical Inspectorate of the relevant state.

This involves submitting the electrical installation drawings to the office of the Chief Electrical Inspector for review. The pre-establishment process usually takes approximately seven days, after which the project proponent may begin the electrical installation.

Once the electrical installation is complete, and all necessary testing has been carried out, the electrical contractor will provide a 'Completion and Test Report' in the prescribed format.

The installation owner will then submit an undertaking through the completion report, confirming that the installation is ready for inspection by the Electrical Inspector.

After submitting the completion report, the process of obtaining CEIG (Chief Electrical Inspectorate of the Government) approval begins. The approval process details are listed in the table below.

Application and Document Submission

Application along with the documents is made to the office of the CEIG. The Junior AEI scrutinize the application and, if found complete in all respect, will forward it to the AEI. Otherwise, he will send a query to the applicant to make relevant changes.

Inspection

During the site inspection, if the inspecting officers are convinced that the said electrical installation is in general conformity with Central Electricity Authority(Measures relating to safety and electric supply)Regulations 2010, necessary safety approval will be issued

Issue of Certificate

Further, on verification of the compliance report, the inspecting officer himself or through the concerned officer, as per DOP, will issue the safety certificate. In case of any issue or defect, he may give a defect notice.

Document needed along with the application for CEIG Approval

  • Completion and Test Report’ issued by a licensed Electrical Contractor
  • NOC from Fire Department/Test Certificate of the Fire Extinguishers.
  • Copies of statutory clearances /approval from Authorities, i.e. Railways/ Defence (AHQ)/Forest Department/ Civil Aviation/ PTCC/National Highways/ HERC/State Government/Power Utilities/CEI/other authorities of State/ Central Government regarding generation / transmission/distribution /consumption of electrical energy.
  • Single line diagram of the installation showing size, rating and details of protection, details of loading, and metering system.
  • Details of earthing provided for the proposed installation.
  • Copy of Licensed Electrical Contractor and Supervisor permit.
  • Scanned copy/ challan of inspection fee paid.
  • Undertaking for the safe operation of the installation.
Note:

If the applicant has applied for Solar Power/ Diesel Generator/ Wind Power and Other Renewable Sources for energization under Regulation 32 of CEA 2010, the following documents will also be needed

  • Copy of generator purchase bill/ invoice
  • Test certificate of the engine, generator and canopy in original
  • List of detailed load list equipment-wise/ Inverter details/ Modular Details
  • Work Completion Report
  • Copy of Contractor Licence
  • Copy of Supervisor Certificate
  • Photo of clearly visible D.G. Set/ Solar Equipment/ Wind Mill/ Other energy sources from 20 Feet Distance.
  • Photo of clearly visible specifications of the nameplate of D.G. set/ Wind Mill/ Inverter/ Other energy sources.

Details to be incorporated in the Electrical Drawings

Single line diagram of the electrical system showing the existing, proposed and future installation details together with protective devices, measuring instruments, and cable sizes along with their capacity and ratings. The inspecting authority will examine the drawing approval application form and check if the applicant has provided all the supporting documents (as mentioned above). The applicant has to address the identified shortcomings in the application within the period specified. The applicant should subsequently submit a revised application form/drawings and/or missing/erroneous documents by resubmitting the application.